Project Management System Evaluation Checklist

“An elegant solution to the wrong problem solves nothing.”
- Bryce’s Law

INTRODUCTION

Commercial Project Management systems (PM) have been available since the early 1970′s. As PC’s proliferated in the workplace, so did PM software, which also brought an ease-of-use element to project management. A multitude of PM products are now available on the market, some expensive, and some very reasonably priced. However, to say all PM packages were created equally would be a gross exaggeration. Each has a specific niche they address in project management or target a specific industry.

As I described in my article, “Why Does Project Management Fail?”, one of the main reasons for failure is because there is a lack of consideration for the magnitude and complexities of project management and, consequently, there is a natural inclination to attack it in piece meal. As a result of the bulletin, I have been asked as to what criteria I would use to evaluate a PM package. Consequently, I have developed the following checklist for evaluating a PM package it its pristine form. I hope it will be of benefit to you.

GENERAL REQUIREMENTS:

The Project Management system should…

  1. Support any type of project – large or small; not just those limited to a specific part of the business (e.g, IT pplications). As such, it should be flexible in application and accommodate any
    and all methods of work effort (new development, maintenance, and modification/improvements).

  2. Distinguish between Direct, Indirect, and Unavailable activities. For background information, see:
    http://www.phmainstreet.com/mba/pride/pmmeth.htm#time

  3. Promote the “Mini-Project Manager” concept. For background information, see:
    http://www.phmainstreet.com/mba/pride/pmmeth.htm#minipm

  4. Provide an integrated approach to support all activities of project management, not just some; this includes Planning, Estimating, Scheduling, Reporting, and Control.

  5. Promote and enforce in-house project management standards; e.g., use of standard methodologies, labor rates, time reporting, detection of estimate/schedule overruns/underruns, etc.

  6. Provide a universally applicable calendar and allow for the specification of a standard reporting cycle.

PLANNING SUPPORT:

The Project Management system should…

  1. Support various Work Breakdown Structures (WBS) – not just a single methodology. This includes controllable levels of WBS (number of levels of detail). Also, provides a library facility for reusable methodologies that can be automatically loaded upon request. Ideally, the WBS can be tied to specific information resources (such as systems, programs, files, etc.) thereby enabling the ability to record and monitor time for a specific information resource.

  2. Support internal project dependencies (work step-to-work step) and external dependencies (project-to-project).

  3. Allow for multiple projects, multiple human resources (both internal employees and external contractors), and multiple assignments for a single human resource. (A “many-to-many” relationship between projects and human resources).

  4. Provide a Skills Inventory to track skills and proficiencies.

  5. Be able to manage project priorities and backlogs of user service requests (business objectives). A “priority modeling” tool is highly desirable to study the impact of change.

ESTIMATING SUPPORT:

The Project Management system should…

  1. Provide for both Detail estimates (for a specific phase of a project) and Order-of-Magnitude (for the entire project). For background information, see:
    http://www.phmainstreet.com/mba/pride/pm20.htm#types

  2. Allow multiple versions of estimates (after all, estimates will inevitably need to be revised).

  3. Provide a means to maintain estimating guidelines and generate tentative estimates accordingly.

SCHEDULING SUPPORT:

The Project Management system should…

  1. Provide for automated calculations using “Effectiveness Rate.” For background information, see:
    http://www.phmainstreet.com/mba/pride/pmmeth.htm#er

  2. Allow multiple versions of schedules (project schedules, like estimates, will change over time).

  3. Provide facilities to manage resource allocations. This includes plotting both estimated and actual project assignments, as well as monitoring “effectiveness rates.”

  4. Be able to calculate critical paths of projects.

REPORTING SUPPORT:

The Project Management system should…

  1. Provide facilities to record and verify time on project assignments.

  2. Provide for the recording of “Estimate to Do” (the amount of time remaining on a given assignment). Note: This is different than “Percent Complete.” For background information, see:
    http://www.phmainstreet.com/mba/pride/pm40.htm#etd

  3. Maintain historical time data to be used in history reports and to update estimating guidelines.

  4. Allow the recording of “out-of-pocket” project expenditures.

  5. Provide a scratchpad facility to record project notes as well as formal reports (e.g. Project Proposals, Cost/Benefit Analysis, Project Audits, etc.).

  6. Provide a standard facility to generate a variety of project reports (a “report writer” facility is ideal).

CONTROL SUPPORT:

The Project Management system should…

  1. Post reported time to projects and to human resources reporting it. Also, post time to information resources to monitor activity. For example, the Order Processing system had 2,342 hours reported when it was created in 1985; 335 hours in 2000; and 246 hours in 2004.

  2. Provide various summary reports to analyze projects and human resources, both by project and by department.

  3. Provide the ability to bill end-users for project costs (Chargeback). This includes chargeback to multiple users at varying rates.

COMPUTER-RELATED CONSIDERATIONS:

The Project Management system should…

  1. Be easy to install and test on the computer.

  2. Be implemented as a cross-platform solution (operates the same on different computers) thus providing machine portability and independence from hardware manufacturers. It should also be easily accessed by all people participating in project management activities (conceivably the whole company) as an integrated approach.

  3. Be easy to learn and use. It should be based on industry design standards (e.g., GUI design standards, on-line Help, use of operating system clipboard, etc.).

  4. Performs reliably and productively in accordance with specifications.

  5. Provide for multi-languages and multi-cultures, such as adapting to local customs for expressing dates, time (am-pm vs. military time), monetary values (Dollars, Pounds, Yen, etc.), and accommodating foreign languages (including the Asian Double Byte Character Set – DBCS).

  6. Provide standard utilities for:
    Monitoring and Administering the system.
    Security – to both administer the system, and login to input data.
    Import/Export data in various formats (Ideally an open interface should be provided).
    File Management – to purge obsolete data, and backup files.

  7. Be provided by a vendor with a reliable reputation for training, service and warranty.

I have described a pretty encompassing system with robust features. As such, a Cost/Benefit Analysis should be prepared to compare price versus the system’s value to the company.

This evaluation checklist should be used as a template and modified accordingly to suit in-house requirements. Good luck.

For additional information on “PRIDE” Project Management, see:
http://www.phmainstreet.com/mba/pride/pm.htm

Tim Bryce is the Managing Director of M. Bryce & Associates (MBA) of Palm Harbor, Florida, a management consulting firm specializing in Information Resource Management (IRM). Mr. Bryce has over 30 years of experience in the field. He is available for training and consulting on an international basis. His corporate web page is at:
http://www.phmainstreet.com/mba/

He can be contacted at: timb001@phmainstreet.com

Copyright © 2006 MBA. All rights reserved.

Share and Enjoy:
  • RSS
  • email
  • Print
  • Twitter
  • StumbleUpon
  • Digg
  • del.icio.us
  • Technorati
  • LinkedIn
  • Tipd
  • Mixx
  • Facebook
  • Diigo
  • Reddit
  • Google Bookmarks

Related posts:

  1. Project Management System Evaluation Checklist
  2. Why Does Project Management Fail?
  3. Why Does Project Management Fail?
  4. Effective Online Project Management System Tool and Task Tracking Software From Inventatechnologies
  5. Imortance of Web Based it Project Management Software Tool and Online Task Management Software

Leave a Reply

Project Management Jobs
Job Search
job title, keywords, company, location jobs by job search
Projects
Resources
  • Submit your sites using SmartSiteSubmit.com's 3-in-1 automatic submission tool: Directory submission, article submission and social bookmarking.
  • Let's go green! Plant a tree by submitting your website to Hive Thrive business web directory - all family-friendly business websites are welcomed.
  • Project management collaboration using cloud apps is proven to be more effective and efficient. Read Cloud Business Review to discover the right cloud apps for your projects.
  • Watch business news and updates in our Business TV site, Bizlogue.com.
  • Want to know what videos are hot on Twitter? SocyPlay.com video search engine can returns you popular videos based on your keyword search.
  • Read DirectoryDaily.com for the latest web directory news, tips and reviews.
  • Looking for parenting tips and children's entertainment? Please visit parenting online resources for recommendations.
  • Need help managing your money better? Read our personal finance blog for down-to-earth personal finance tips.
  • Quantec Geoscience to Roll Out Global Inspection Management Solution - MarketWatch (press release)
    Quantec Geoscience to Roll Out Global Inspection Management SolutionMarketWatch (press release)Field ID's cloud-based system has been implemented across Quantec Geoscience's project management, equipment inspection and safety compliance processes in Canada, allowing 50 key users to manage data for almost 10000 daily inspection events in a secure .. […]
  • Civil servants to get project management lessons - ComputerworldUK
    Telegraph.co.ukCivil servants to get project management lessonsComputerworldUKBy Anh Nguyen | Computerworld UK | Published 12:40, 07 February 12 Francis Maude, Cabinet Office Minister, has announced plans to set up an academy to give lessons to senior civil servants on how to manage large government projects.More than half of government projects behind sched […]
  • Vision Technology Services Looks to Continue Growth in 2012 - PR Web (press release)
    PR Web (press release)Vision Technology Services Looks to Continue Growth in 2012PR Web (press release)Vision Technology Services, the premier provider in Project Management Services and IT Jobs in Maryland, finished 2011 with local and regional accolades that leaves a sense of optimism for the dawning year. In early December, Vision was recognized by ...and […]
  • BizPAD Project Management Software Solution Now Under New Ownership - San Francisco Chronicle (press release)
    BizPAD Project Management Software Solution Now Under New OwnershipSan Francisco Chronicle (press release)Cloud based BizPAD.com, a online project management software solution has been sold to Greg Writer an avid user of the program and a raving fan of its simplicity. When previous owner Rick Raddatz, a former Microsoft employee and Internet entrepreneur, .. […]
  • Project Management Software Project Insight Adds New Project Management Webinars - MarketWatch (press release)
    Project Management Software Project Insight Adds New Project Management WebinarsMarketWatch (press release)IRVINE, CA, Feb 07, 2012 (MARKETWIRE via COMTEX) -- Project and portfolio management software, Project Insight is partnering with Core Performance Concepts, Inc. to offer a refreshed curriculum of 23 unique project management webinars for 2012.and more  […]
  • Meridian signs two new partners for Middle East - ITP.net
    ITP.netMeridian signs two new partners for Middle EastITP.netBy Mark Sutton Published February 7, 2012 Construction project management software specialists Meridian Systems, has added two new partners for the Middle East region. Meridian has signed Value Added Reseller agreements with two companies, ...Zone Technology Joins the Meridian Systems Partner Netwo […]
  • UMT represents SA at Microsoft Project Conference 2012 - ITWeb
    UMT represents SA at Microsoft Project Conference 2012ITWebOne of its customers, mining giant Exxaro, will also be presenting its enterprise-wide deployment of a project management system based on the Microsoft Enterprise Project Management (EPM) system. UMT Consulting SA is the first company in Africa and ...and more » […]
  • NBRI Celebrates 30 Years of Research Excellence - Houston Chronicle
    NBRI Celebrates 30 Years of Research ExcellenceHouston ChronicleMelissa quickly moved into a senior position and oversaw the project management team. She instituted tracking systems to facilitate team collaboration in managing work flow and enhancing quality assurance checkpoints. As a Senior Project Manager, ...and more » […]
  • Digital Celerity Joins the Prestigious Group of Organizations Approved by ... - San Francisco Chronicle (press release)
    Digital Celerity Joins the Prestigious Group of Organizations Approved by ...San Francisco Chronicle (press release)Digital Celerity LLC announces it is now approved by Project Management Institute to become a PMI Registered Education Provider (REP) effective Jan 15, 2012. Digital Celerity LLC announces it is now approved by Project Management Institute to b […]
Archives
Stats